Connection to the electricity and gas network
  • CategoryCommercial households

Connection to the electricity network

Connection of existing or future construction facilities of entrepreneurs with the required capacity up to 150 kW (including 150 kW from the existing 0.4 kV network) to an electricity supply network is realized in accordance with the Decree of the President of the Republic of Azerbaijan No. 1313 dated April 4, 2017.

According to this rule, applications related to the preparation and issuance of project documents, technical specifications, as well as connection to the electricity supply networks are implemented through e – Government Portal, SME houses and “ASAN Kommunal” centers (in regions where “ASAN Kommunal” centers have not been established - “ASAN service” centers until these centers are established).

On the basis of a request (application), the Technical Council together with the member agencies, with the help of electronic maps, determines: the nearest electricity source to the construction site; the optimal route from the electricity source to the construction site for the supply of electricity (power); and the agencies required to review the construction of power lines.

In general, the connection to the electricity supply network is realized in 2 stages:

1. making an application;

2. carrying out construction and installation works and physically connecting to the electricity supply network.

During the physical connection, technical requirements, project estimate documents, act of connection and purchase and sale agreement shall be submitted to entrepreneur.

 

List of required documents


  • Customer’s Taxpayer Identification Number (TIN); 
  • report on capacity and quality indicators of required electric energy (active and reactive power of electrical installations and reliability category);
  • copy of the document confirming the right of ownership or other property rights of the construction facility that considered to be connected to electricity supply network;
  • document proving payment of act of connection;
  • customer’s postal and e-mail address (if e-mail available).

Service fee


Connection of existing or future construction facilities with the required power up to 150 kW (including 150 kW from the existing 0.4 kV network) to the electricity supply networks is realized in accordance with the Order of the Cabinet of Ministers of the Republic of Azerbaijan No. 180 dated 27 April 2018.


Duration


 

 
Up to 150 kW

Selection of route and preparation of technical specifications and project document

10 days

Connection to the electricity supply network

10 days

Over 150 kW

Provision of technical specifications

10 work days

Preparation of project estimate document

5 work days

Connection to the electricity supply network

Determined based on project estimate documen

 


Application for connection to the gas supply network

Non-domestic groups may apply to "ASAN service" or "ASAN Kommunal" centers to connect existing or construction facilities to the gas supply network
 

List of required documents


  • Application;
  • Relevant letter addressed to the representative of legal entity and copy of the representative’s identity card (if legal entity);Copy of Taxpayer Identification Number (TIN) and identity card (in the cases when individual is engaged in entrepreneurial activity without establishing a legal entity);
  • Documents confirming the right to property (extract from the relevant document, decree, order of local municipality).
 

Service Fee – Free


Duration - 20 working days